Question: A simple CPM network has four activities, A, B, C and D as shown below. The latest finish time (LF) for activity B is Activity

A simple CPM network has four activities, A, B, C and D as shown below. The latest finish time (LF) for activity B is

Activity

Duration

Immediate

Predecessors

A

19

--

B

18

--

C

7

A,B

D

5

B

21

20

26

18

19