Question: A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate
A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity duration's are A=4, B=3, C=8)
What is the critical path?
A. The critical path is A-B-C, duration 15.
B. The critical path cannot be determined without knowing PERT expected activity times.
C. The critical path is A-C, duration 12.
D. The critical path is A-B-C, duration 13.5
E. The network has no critical path.