A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A-4, B=3, C-5. O The critical path is A-B-C, duration 12. The critical path cannot be determined without knowing PERT expected activity times. O The network has no critical path. The critical path is A-B-C, duration 9. O The critical path is A-C, duration 10.5