Question: Q2: A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an
Q2: A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B
and of C. B is an immediate predecessor of C. The activity durations are A = 4, B = 3, C = 8.What is the duration of the critical path.