Question: A simple CPM network has three activities, A, B, and C.A is an immediate predecessor of B and of C. B is an immediate predecessor

A simple CPM network has three activities, A, B, and C.A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=8.

a. The critical path is A-B-C, duration 13.5

b. The critical path is A-C, duration 12.

c. The critical path cannot be determined without knowing PERT expected activity times.

d. The network has no critical path

e. The critical path is A-B-C, duration 15

Given an actual demand of 61, a previous forecast of 58, and an of .3, what would the forecast for the next period be using simple exponential smoothing?

a. 58.9

b. 57

c. 61

d. 61.5

e. 45.5

Please please, I don't have enough time to help me

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!