Question: A simple CPM network has three activities, D , E , and F . D is an immediate predecessor of E and of F .

A simple CPM network has three activities, D, E, and F.D is an immediate predecessor of E and of F.E is an immediate predecessor of F. The activity durations are D=4,E=3,F=8.
Select the correct response:
Slack at D is 3 units
The critical path is D-F, duration 12
Both a and c are true
The critical path is D.E.F. duration 15
Slack at E is 3 units
 A simple CPM network has three activities, D, E, and F.D