Question: A simple CPM network has three activities, D , E , and F . D is an immediate predecessor of E and of F .
A simple CPM network has three activities, D E and F D is an immediate predecessor of E and of F E is an immediate predecessor of F The activity durations are D E F
Answer: A
The critical path is DEF duration
The critical path is DF duration
The critical path is DF duration
There are critical paths
There is no any critical path