Question: A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate

A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=6. a. Slack at E is 3 periods. b. The critical path is D-E-F, duration 12. c. Slack at D is 0 periods. d. The critical path is D-F, duration 10. e. Both A and c are true