Question: A: Site Selection and Acquisition Duration: 1 0 weeks Optimistic: 8 weeks Most Likely: 1 0 weeks Pessimistic: 1 2 weeks B: Design and Planning

A: Site Selection and Acquisition
Duration: 10 weeks
Optimistic: 8 weeks
Most Likely: 10 weeks
Pessimistic: 12 weeks
B: Design and Planning
Duration: 12 weeks
Optimistic: 10 weeks
Most Likely: 12 weeks
Pessimistic: 14 weeks
Predecessors: A
C: Obtaining Necessary Permits
Duration: 8 weeks
Optimistic: 6 weeks
Most Likely: 8 weeks
Pessimistic: 10 weeks
Predecessors: B
D: Hiring Contractors and Suppliers
Duration: 4 weeks
Optimistic: 3 weeks
Most Likely: 4 weeks
Pessimistic: 5 weeks
Predecessors: B
E: Excavation and Grading
Duration: 6 weeks
Optimistic: 4 weeks
Most Likely: 6 weeks
Pessimistic: 8 weeks
Predecessors: C, D
F: Foundation and Framing
Duration: 10 weeks
Optimistic: 8 weeks
Most Likely: 10 weeks
Pessimistic: 12 weeks
Predecessors: E
G: Mechanical, Electrical, and Plumbing (MEP)
Duration: 8 weeks
Optimistic: 6 weeks
Most Likely: 8 weeks
Pessimistic: 10 weeks
Predecessors: F
H: Exterior Finishes and Landscaping
Duration: 6 weeks
Optimistic: 4 weeks
Most Likely: 6 weeks
Pessimistic: 8 weeks
Predecessors: G
I: Interior Finishes and Equipment Installation
Duration: 10 weeks
Optimistic: 8 weeks
Most Likely: 10 weeks
Pessimistic: 12 weeks
Predecessors: G
J: Final Inspections and Certificate of Occupancy
Duration: 4 weeks
Optimistic: 3 weeks
Most Likely: 4 weeks
Pessimistic: 5 weeks
Predecessors: H, I
draw a network for this project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!