Question: A small Factory needs an MPS and MRP for one of their products (product X), the demand forecast and customer orders are shown in the
A small Factory needs an MPS and MRP for one of their products (product X), the demand forecast and customer orders are shown in the table.

Fixed lot size is 50, lead time 1 week and available inventory 50
For the elaboration of the MRP, the BOM for product X is as shown in the diagram

| Component | Lot for lot size | Available inventory |
| A | 60 | 300 |
| B | 20 | 50 |
| C | 50 | 50 |
| D | 10 | 50 |
develop a master production schedule and then a material requirements plan:
Thank you :)
Weeks 1 21 3 51 61 8 Demand Forecast 101 201 151 15 25 25 10 25 Customer orders 13 18) 15 Product X A (3) - 1 week B (1) - 1 week C (1) - 2 weeks C (1) - 2 weeks D (3) - 1 week Weeks 1 21 3 51 61 8 Demand Forecast 101 201 151 15 25 25 10 25 Customer orders 13 18) 15 Product X A (3) - 1 week B (1) - 1 week C (1) - 2 weeks C (1) - 2 weeks D (3) - 1 week
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts