Question: A small Factory needs an MPS and MRP for one of their products (product X), the demand forecast and customer orders are shown in the

A small Factory needs an MPS and MRP for one of their products (product X), the demand forecast and customer orders are shown in the table.

A small Factory needs an MPS and MRP for one of their

Fixed lot size is 50, lead time 1 week and available inventory 50

For the elaboration of the MRP, the BOM for product X is as shown in the diagram

products (product X), the demand forecast and customer orders are shown in

 

Component

Lot for lot size

Available inventory

A

60

300

B

20

50

C

50

50

D

10

50

develop a master production schedule and then a material requirements plan:

Thank you :)

Weeks 1 21 3 51 61 8 Demand Forecast 101 201 151 15 25 25 10 25 Customer orders 13 18) 15 Product X A (3) - 1 week B (1) - 1 week C (1) - 2 weeks C (1) - 2 weeks D (3) - 1 week Weeks 1 21 3 51 61 8 Demand Forecast 101 201 151 15 25 25 10 25 Customer orders 13 18) 15 Product X A (3) - 1 week B (1) - 1 week C (1) - 2 weeks C (1) - 2 weeks D (3) - 1 week

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!