Question: A software development project completed the initiation phase. The technical design was approved by the project steering committee, Later, it was discovered that the design
A software development project completed the initiation phase. The technical design was approved by the project steering committee, Later, it was discovered that the design will impact the company's production system. A new technical design must be found and this could delay the project by 3 months, What should the project manager do first? Log the technical design delay as a risk in the project risk log. Ask the steering committee to approve a new technical design. Continue with the approved design so that the project is not delayed Set up a steering committee session to review the project delay
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
