Question: A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design
A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company's production system. A new technical design must be found and this could delay the project by months.What should the project manager do first?A Set up a steering committee session to review the project delay.B Continue with the approved design so that the project is not delayed.C Log the technical design delay as a risk in the project risk logD Ask the steering committee to approve a new technical design.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
