Question: A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design
A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company's production system. A new technical design must be found and this could delay the project by 3 months. What should the project manager do first? Continue with the approved design so that the project is not delayed. Set up a steering committee session to review the project delay. Ask the steering committee to approve a new technical design. Log the technical design delay as a risk in the project risk log