Question: A software development project is based on the following: Activity Predecessor Successor Normal Time Normal Cost Crash Time Crash Cost A C 8 $ 2

A software development project is based on the following:
Activity Predecessor Successor Normal
Time Normal
Cost Crash
Time Crash
Cost
A C 8 $ 2007 $ 300
B D 103006400
C A E 280011000
D B E 42002300
E C, D 1550011800
The project manager determines it is necessary to shorten the completion time for the project.
a. If she decides to crash the project by one day, what activity should be crashed?
multiple choice 1
Activity A
Activity B
Activity D
Activity E
b. What is the total project cost after crashing by one day?
c. If she decides to crash by two days, what activity should be crashed next?
multiple choice 2
Activity A
Activity B
Activity D
Activity E
d. What is the total project cost after crashing by two days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!