Question: Item16 eBookReferencesView previous attemptItem 16 A software development project is based on the following: Activity Predecessor Successor Normal Time Normal Cost Crash Time Crash Cost

Item16 eBookReferencesView previous attemptItem 16 A software development project is based on the following: Activity Predecessor Successor Normal Time Normal Cost Crash Time Crash Cost A C 8 $ 200 7 $ 300 B D 10 300 6 400 C A E 2 800 1 1000 D B E 4 200 2 300 E C, D 15 500 11 800 The project manager determines it is necessary to shorten the completion time for the project. a. If she decides to crash the project by one day, what activity should be crashed? multiple choice 1 Acti