Question: A software development project is based on the following: Activity Predecessor Successor Normal Time Normal Cost Crash Time Crash Cost A C 8 $ 2

A software development project is based on the following:
Activity Predecessor Successor Normal
Time Normal
Cost Crash
Time Crash
Cost
A C 8 $ 2007 $ 300
B D 103006400
C A E 280011000
D B E 42002300
E C, D 1550011800
a. What are the normal project completion time and normal cost?
b. What is the critical path?
multiple choice 1
C-E
A-C-E
D-E
B-D-E
c. Teams of software engineers working on activities A and B agree to combine their efforts and to label their new activity as F. They believe that, by working together, they can complete their combined work in nine periods. What is the new normal project completion time and the new critical path?
multiple choice 2
F-D-E
C-E
F-C-E
D-E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!