Question: A software development project is based on the following: Activity Predecessor Successor Normal Time Normal Cost Crash Time Crash Cost A C 8 $ 200
A software development project is based on the following:
| Activity | Predecessor | Successor | Normal Time | Normal Cost | Crash Time | Crash Cost | ||
| A | C | 8 | $ | 200 | 7 | $ | 300 | |
| B | D | 10 | 300 | 6 | 400 | |||
| C | A | E | 2 | 800 | 1 | 1000 | ||
| D | B | E | 4 | 200 | 2 | 300 | ||
| E | C, D | 15 | 500 | 11 | 800 | |||
a. What are the normal project completion time and normal cost?
b. What is the critical path?
-
C-E
-
A-C-E
-
D-E
-
B-D-E c. What is the new project completion time and the new critical path?