Question: A software development project is based on the following: Activity Predecessor Successor Normal Time Normal Cost Crash Time Crash Cost A C 8 $ 200

A software development project is based on the following:

Activity Predecessor Successor Normal Time Normal Cost Crash Time Crash Cost
A C 8 $ 200 7 $ 300
B D 10 300 6 400
C A E 2 800 1 1000
D B E 4 200 2 300
E C, D 15 500 11 800

a. What are the normal project completion time and normal cost?

b. What is the critical path?

  • C-E

  • A-C-E

  • D-E

  • B-D-E c. What is the new project completion time and the new critical path?