Question: A task in a network has... Early Start = 2 Early Finish = 4 Late Start = 5 Late Finish = 7 What is its

A task in a network has...
Early Start =2
Early Finish =4
Late Start =5
Late Finish =7
What is its slack?
Group of answer choices
1
2
3
4
5