Question: 1.) A task in a network has... Early Start = 2 Early Finish = 4 Late Start = 5 Late Finish = 7 What is
1.) A task in a network has...
Early Start = 2
Early Finish = 4
Late Start = 5
Late Finish = 7
What is its slack?
A) 1
B) 2
C) 3
D) 4
E) 5