Question: A task was timed at 6 5 cycles. On average, it took 1 . 1 0 minutes per cycle. The performance rating was 8 6
A task was timed at cycles. On average, it took minutes per cycle. The performance rating was percent, and the workday allowance is percent. Find the observed time, normal time, and standard time Do not round intermediate calculations Round the final answers to decimal places and calculations are needed for grading
Step by Step Solution
There are 3 Steps involved in it