Question: need as soon as A task was timed for 60 cycles. It took an average of 1,10 minutes per cycle. The performance rating was 80
A task was timed for 60 cycles. It took an average of 1,10 minutes per cycle. The performance rating was 80 percent, and workday allowance is 5 percent. Determine each of the following. (Do not round intermediate calculations. Round the final answers to 2 decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts