Question: A technique used for constructing a schedule model, where activities or tasks are represented by nodes and are graphically linked by one or more logical

A technique used for constructing a schedule model, where activities or tasks are represented by nodes and are graphically linked by one or more logical relationships to show the sequence the activities or tasks are to be performed is the _ O precedence diagramming method flow diagramming methodology O leads and lags determination decomposition method