Question: A three-phase pre-timed signal system is to be designed to have a standard amber period of 3s and all-red period of 2s for each

A three-phase pre-timed signal system is to be designed to have a 

A three-phase pre-timed signal system is to be designed to have a standard amber period of 3s and all-red period of 2s for each phase change, for the intersection shown below. Using the data in the table below and Webster s method, determine i. The Optimum cycle length and the green time to be allocated to each phase (CR,10) ii. Diagrammatic representation of signal sequence (EV,5) Assume the volumes in the table to be design hourly volumes (DHV). B A Phase Lane group 2 3 Z Critical volume (peu/hr) 351 424 150 Saturation flow (pcu hr) 1800 1800 1600

Step by Step Solution

3.42 Rating (146 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Date Page Question4 a All red time R 2 a Total lost time L 2ntR n Number ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!