Question: A time study was made on an assembly task, and the average cycle time was found to be 1.87 min. The time-study rating of the

A time study was made on an assembly task, and the average cycle time was found to be 1.87 min. The time-study rating of the observed operators performance was 90%. This particular task has a 23 min fatigue allowance, a 10 min/shift delay allowance, and a 24 min/shift personal allowance. What is the standard time for this task?