Question: A typical example will clarify the procedure of line balancing. Ex: A company is setting an assembly line to produce 192 units per 8 hour

A typical example will clarify the procedure of line balancing. Ex: A company is setting an assembly line to produce 192 units per 8 hour shift. The information regarding work elements in terms of times and intermediate predecessors are given below: Time (Sec) Work element A B D E F G H I J Total 40 80 30 25 20 15 120 145 130 115 720 Immediate predecessor None A D.E.F B B B A G H C.I 1. What is the desired cycle time? 2. What are the theoretical numbers of stations? 3. Use largest work element time rule to work out a solution on a precedence diagram, 4. What are efficiency and balance delay of the solution obtained