Question: a ) Using the Precedence Diagramming Method, analyse the data in Table 1 and complete the Table. b ) Identify the Critical Path ( s

a) Using the Precedence Diagramming Method, analyse the data in Table 1 and complete the Table.
b) Identify the Critical Path(s).
c) What is the duration of the Project?
d) Compute the Total Float and Free Float for the activities:
D; E; F; K and M
e) Draw the histogram for Resource X based on Earliest Start Times.
f) Describe three (3) decisions you may possibly consider making to resolve any schedule variances. [3]
Activity Name Activity Duration (weeks) Preceding Activity Dependency Type Allocated Resources Earliest Start Time Earliest Finish time Latest start Time Latest Finish Time Total Float Critical or Not Critical
START 0 Nil --------
A 3 Start F - S 2X,
B 2 A F - S 3X
C 3 B F - S 3X.4M
D 4 START F - S 2X,2M
E 3 D F - S 2X,2M
F 5 E F - S 1x
G 2 F,C F - S 2X,2M
H 4 G F - S -
J 4 START F - S 2X,4M
K 1 J F - S 4X,2M
L 3 E, K F - S X, M
M 1 L F - S 3X,3M
N 4 F, M F - S 2X
P 2 H, N F - S X
FINISH 0 P F - S

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!