Question: a ) Using the Precedence Diagramming Method, analyse the data in Table 1 and complete the Table. b ) Identify the Critical Path ( s
a Using the Precedence Diagramming Method, analyse the data in Table and complete the Table.
b Identify the Critical Paths
c What is the duration of the Project?
d Compute the Total Float and Free Float for the activities:
D; E; F; K and M
e Draw the histogram for Resource X based on Earliest Start Times.
f Describe three decisions you may possibly consider making to resolve any schedule variances.
Activity Name Activity Duration weeks Preceding Activity Dependency Type Allocated Resources Earliest Start Time Earliest Finish time Latest start Time Latest Finish Time Total Float Critical or Not Critical
START Nil
A Start F S X
B A F S X
C B F S XM
D START F S XM
E D F S XM
F E F S x
G FC F S XM
H G F S
J START F S XM
K J F S XM
L E K F S X M
M L F S XM
N F M F S X
P H N F S X
FINISH P F S
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock