Question: A waste facility is processing 3000 tons of garbage per day with a standard deviation of 300 tons. If waste would be sourced in 1000

A waste facility is processing 3000 tons of

A waste facility is processing 3000 tons of garbage per day with a standard deviation of 300 tons. If waste would be sourced in 1000 ton barges, average lead time would be 2 days with a standard deviation of 0.5 days. How much safety stock do we need to guarantee a 90% fill rate under continuous review? a) less than 1600 tons b) between 1600 and 1800 tons 10 c) between 1800 and 2000 tons d) more than 2000 tons