Question: A. What is the ES for Activity E? B. What is the LS for Activity F? C. What are the slack for the start of

A. What is the ES for Activity E? B. What is the

A. What is the ES for Activity E?

B. What is the LS for Activity F?

C. What are the slack for the start of Activities C and I?

D. What is the slack for the end of Activity I

E. What is the lenght of the project?

Given the following information, compute the early, late, and slack times for the project network. ID Task Duration Predecessor Additional Lag Relationships Lag Finish-start A to B 11 B A B D E F G H I J 2 Post Signs Prepare Site Lights Dig Trenches Lay Pipe Back Fill Pave Paint Parking Lines Signage Open Lot 5 6 4 5 6 2 1 1 1 Start-start D to E Start-start E to F 1 B D E F G G C, H, I Finish-start G to H 3 Task 10 A Lag 11 Lag 3 1 Post Signs Prepare Ste Lights Die Trenches Lay Pipe Back Fil D D G 1 F G Pare 5 - Paint Parking Lines Signage Open Lot Lag 2 Lag 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!