Question: A work package is expected to take 4 weeks to complete. Its budget is $200. The work package is 50% complete, and $150 has been
A work package is expected to take 4 weeks to complete. Its budget is $200. The work package is 50% complete, and $150 has been spent. What is the work package's earn value