Question: 18 3 pts A work package is expected to take 4 weeks to complete. Its budget is $200. The work package is 50% complete, and
18 3 pts A work package is expected to take 4 weeks to complete. Its budget is $200. The work package is 50% complete, and $150 has been spent. What is the work package's earn value? $100 $150 $200 $800