Question: ABC Co. was asked to complete a process improvement project for their favorite client, XYZ Co. The activities, time requirements, and direct cost considerations are
ABC Co. was asked to complete a process improvement project for their favorite client, XYZ Co. The activities, time requirements, and direct cost considerations are indicated below. Indirect/overhead costs are $2,000 per week. Because XYZ Co. is under time pressure to increase productivity, there is a penalty of $3,000 per week for every week the project extends beyond 8 weeks.
a.) How long will the project take before crashing?
b.) What is the minimum cost schedule (time)?
c.) What is the minimum cost ($)?


Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
