Question: ABC Co. was asked to complete a quality control project for their favorite client, XYZ Co. The activities, time requirements, and direct cost considerations are
ABC Co. was asked to complete a quality control project for their favorite client, XYZ Co. The activities, time requirements, and direct cost considerations are listed below. In addition, indirect costs/overhead are $2,000 per week. Because XYZ Co. is under time pressure to improve quality, there is a penalty of $3,000 per week for every week the project extends beyond 14 weeks.
a.) How long will the project take before crashing?
b.) What is the minimum cost schedule (time)?
c.) What is the minimum cost ($)?