Question: ABC Inc. must make a decision on its current capacity for next year. Estimated profits (in $000s) based on next years demand are shown in
ABC Inc. must make a decision on its current capacity for next year. Estimated profits (in $000s) based on next years demand are shown in the table below.
Next Years Demand Alternative Low High Expand $100 $200 Subcontract $50 $120 Do nothing $40 $50
Using the information above, which alternative should be chosen based on the maximin criterion?
Please explain and show working. Thanks. Will upvote!