Question: According to the critical path method analysis, the Earliest Start time is 7 days and the Latest Start time is 9 days for one particular

According to the critical path method analysis, the Earliest Start time is 7 days and the Latest Start time is 9 days for one particular activity. Assume that the activity duration is 3 days. Which of the following statements is true?

Answers:

The Latest Finish is 12 days

The Earliest Finish is 12 days

This activity is on a critical path

Delaying this activity by 3 days will not affect the project duration

None of the above