Question: According to the critical path method analysis, the Earliest Start time is 7 days and the Latest Start time is 9 days for one particular
According to the critical path method analysis, the Earliest Start time is 7 days and the Latest Start time is 9 days for one particular activity. Assume that the activity duration is 3 days. Which of the following statements is true?
Answers:
| The Latest Finish is 12 days | ||
| The Earliest Finish is 12 days | ||
| This activity is on a critical path | ||
| Delaying this activity by 3 days will not affect the project duration | ||
| None of the above |