Question: Activities N and D must be completed before activity C can start. Activities N, D, and A must be completed before activity F can start
Activities N and D must be completed before activity C can start.
Activities N, D, and A must be completed before activity F can start
Activities P and F must be completed before activity M can start
Activity F must be complete before activity C can start.
The duration of activities N, D, and A are 37, 32, and 41 days, respectively.
The duration of activities P and F are 35 and 36 days, respectively.
Furthermore LS(M) = 145 and LS(C) = 119.
Find the value of LS(N)
Activities N, D, and A must be completed before activity F can start
Activities P and F must be completed before activity M can start
Activity F must be complete before activity C can start.
The duration of activities N, D, and A are 37, 32, and 41 days, respectively.
The duration of activities P and F are 35 and 36 days, respectively.
Furthermore LS(M) = 145 and LS(C) = 119.
Find the value of LS(N)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock