Question: Activity 5 cannot begin until Activity 4 has been underway for at least 2 daysis which type of restriction? Start to Start Finish to Start

"Activity 5 cannot begin until Activity 4 has been underway for at least 2 days"is which type of restriction?
Start to Start
Finish to Start
Start to Finish
Finish to Finish
 "Activity 5 cannot begin until Activity 4 has been underway for