Question: Activity A 8 NG D E G immediate Predecessor A A B,C 10 DE H GF What is the variance of the entical path? O

Activity A 8 NG D E G immediate Predecessor A A
Activity A 8 NG D E G immediate Predecessor A A B,C 10 DE H GF What is the variance of the entical path? O a 1:362 Ob.5.144 O2.362 Od 4.364 0,5222 Optimistic 5 14 Most Likely 3 6 12 55 14 Pessimistic 4 0 9 15 0 14 19 0 Signa 0333 1.33 0 0.333 10 1333 1.67 Varance 0.111 1 1.78 20 0.111 a 1.78 1.302 1 points Save

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!