Question: : Activity A B C D E F G H Time 7 7 8 8 7 3 9 7 A. Identify the critical path. B.

: Activity A B C D E F G H Time 7 7 8 8 7 3 9 7 A. Identify the critical path. B. How much time will be needed to complete this project? fill in the blank ____ weeks. C. Can activity F be delayed without delaying the entire project? If so, by how many weeks? _______If "No" enter "0". ___________weeks. D. Can activity C be delayed without delaying the entire project? If so, by how many weeks? ________- If "No" enter "0". __________. E. What is the schedule for activity B? Enter 0 if your answer is zero. Schedule for activity B Earliest Start ______ Latest Start__________ Earliest Finish__________- Latest Finish____
Consider the following project network and activity times (in weeks): C H A D F Finish Start B G G B G F H A D E F 30 Activity Time 7 9 7 7 8 3 8 7 a. Identify the critical pathStep by Step Solution