Question: Activity A B C D E F G H I J K L M N O Duration (in days) 14 20 4 12 20 15

Activity A B C D E F G H I J K L M N O Duration (in days) 14 20 4 12 20 15 11 9 11 4 79 3 10 5 6

Precedents For A has nothing FOR B HAS NOTJINH FOR C is B For d is f For e is c,d For f is b For g is e For h is f For i is h,g For j is h For k is a,b For l is a For m is l For n is m For o is n Enter the FLOAT associated with each activity in the boxes below. Task A Task B Task C Task D Task E Task F Task G Task H Task I Task J Task K Task L Task M Task N Task O