Question: Activity A B C D E F G H I J K Immediate Predecessors A A A B B C, F D H G, I

Activity A B C D E F G H I J K Immediate Predecessors A A A B B C, F D H G, I E, J Optimistic 2 3 4 6 4 5 8 4 4 3 4 Most Likely 6 8 7 9 7 7 11 8 9 12 7 Pessimistic 9 11 14 13 12 14 6 16 11 18 13 14 1. Draw the network diagram by using the Activity on Node method (5 pt). 2. Label each activity time under each node (5 pt). 3. Upload your network diagram in the .pdf (0 points for non-pdf) file format by clicking on the text box below and selecting the paper clip symbol.
 Activity A B C D E F G H I J

1. Draw the network diagram by using the Activity en Node method ( 5pt). 2. Label each activity time under each node ( 5 pt). 3. Upload your network diagram in the pdf ( 0 points for non-pdf) file format by clicking on the text box below and selecting the paper clip symbol

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!