Question: Activity Activity Time (daydays) Immediate Predecessor(s) A 4 long dash B 1 long dash C 4 A D 4 B E 6 C, D Calculate

Activity

Activity Time

(daydays)

Immediate Predecessor(s)

A

4

long dash

B

1

long dash

C

4

A

D

4

B

E

6

C, D

Calculate the slack for each activity. (Enter your responses as integers.)