Question: Activity Activity Time (daydays) Immediate Predecessor(s) A 4 long dash B 1 long dash C 4 A D 4 B E 6 C, D Calculate
| Activity | Activity Time (daydays) | Immediate Predecessor(s) |
| A | 4 | long dash |
| B | 1 | long dash |
| C | 4 | A |
| D | 4 | B |
| E | 6 | C, D |
Calculate the slack for each activity. (Enter your responses as integers.)