Question: Activity Activity Time (days) Immediate Predecessor(s) A 3 B 3 A C 5 A D 4 B E 1 B F 5 B, C G
| Activity | Activity Time (days) | Immediate Predecessor(s) |
| A | 3 | |
| B | 3 | A |
| C | 5 | A |
| D | 4 | B |
| E | 1 | B |
| F | 5 | B, C |
| G | 2 | D, E |
| H | 3 | F |
| I | 5 | F |
| J | 6 | G, H, I |

The critical path is A-C-F-I-J and the project duration is 24 days.
How much slack is in each of the activities G, H, and I?
| Activity | Activity Time (days) | On critical path? | Slack (days) |
| G | 2 | No Yes | enter your response here |
| H | 3 | Yes No | enter your response here |
| I | 5 | Yes No | enter your response here |