Question: Activity ( Bolded is the deliverable ) Most Likely Duration ( unit = days ) Immediate Predecessor 1 AT Data Center Project 2 1 .
Activity
Bolded is the deliverable
Most Likely Duration
unit days
Immediate Predecessor
AT Data Center Project
Team Meeting
Hire Contractors
Network Design
Ventilation System
Order Ventilation System
Install Ventilation System
New Racks
Order Racks
Install Racks
Power Supplies and Cables
Order Power Supplies and Cables
Install Power Supplies
Install Cables
Renovation of Data Center
City Inspection
Switchover Ops Checks
Validation Tests with Clients
Project Closure Meeting