Question: ACTIVITY BUDGET TO COMPLETE CURRENT WORK PERFORMED CURRENT PROGRESS SHOULD BE A 18,000 80% 75% B 24,000 60% 50% C 8.000 100% 80% What is
| ACTIVITY | BUDGET TO COMPLETE | CURRENT WORK PERFORMED | CURRENT PROGRESS SHOULD BE |
| A | 18,000 | 80% | 75% |
| B | 24,000 | 60% | 50% |
| C | 8.000 | 100% | 80% |
What is the Schedule Performance Index?
Step by Step Solution
There are 3 Steps involved in it