Question: Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 5. B's earliest finish is 15, while
Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 5. B's earliest finish is 15, while C's is 18. F's late start is 23. Which of the following is definitely TRUE?
C has no slack, and is critical.
B has no slack, and is critical.
F is not critical, and has slack.
D is critical, and has a slack of five days.
C must be started after B is finished.