Question: Activity Depends on Activity Duration ( days ) Optimistic Most Likely Pessimistic A - 2 5 1 4 B - 3 1 2 2 1
Activity Depends on Activity Duration days
Optimistic Most Likely Pessimistic
A
B
C A
D B
E CD
F B
Total
a Determine expected duration te and sigma Te for each activity. points
b Determine Te and sigma Te points
c What is the probability that: points
i The project will be completed in days.
ii The project will be completed in more than days.
iii. The project will take between and days.
d If the owner wishes to work on a probability of completion of what will be the earliest project time? points
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
