Question: Consider the following work breakdown structure: Start Finish Node Node Activity A Duration (days) Optimistic Most Likely Pessimistic 62 65 68 28 30 32 2

Consider the following work breakdown structure:

Consider the following work breakdown structure: Start Finish Node Node Activity A Duration (days) Optimistic Most Likely Pessimistic 62 65 68 28 30 32 2 1 1 3 2 4 62 70 78 3 4 32 41 44 0 0 0 1 1 2 1 4 5 55 62 65 4 6 32 38 43 5 7 62 66 74 6 7 32 35 39 What is the probability that this project will be completed within 270 days? (Keep 3 decimal places)