Question: Consider the following work breakdown structure: Start Activity Node Finish Node 2 Duration (days) Optimistic Most Likely. Pessimistic 41 50 59 A 1 1 3

Consider the following work breakdown structure:

Consider the following work breakdown structure: Start Activity Node Finish Node 2 Duration (days) Optimistic Most Likely. Pessimistic 41 50 59 A 1 1 3 54 66 62 70 2 4 58 82 3 4. 32 41 44 Inmono 4. 5 60 75 79 4 6 25 30 36 5 7 44 52 62 6 7 32 40 41 What is the estimated expected (mean) time for project completion? (Keep 1 decimal place)