Question: Activity Depends on Duration Estimate( most likely) Duration Estimate( Best Case ) DurationEstimate(worst case) A - 4 2 8 B - 5 2 6 C
| Activity | Depends on | Duration Estimate( most likely) | Duration Estimate( Best Case ) | DurationEstimate(worst case) |
| A | - | 4 | 2 | 8 |
| B | - | 5 | 2 | 6 |
| C | A,B | 5 | 4 | 7 |
Consider a simple project (above) with 3 activities A, B, C. If we work with the optimistic best case estimate and use critical path method, what is the project completion time calculated by CPM?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
