Question: Activity Depends on Duration Estimate(most likely Duration Estimate(best case) Duration Estimate( worst case) A - 4 2 8 B - 5 2 6 C A,B

Activity Depends on Duration Estimate(most likely Duration Estimate(best case) Duration Estimate( worst case)
A - 4 2 8
B - 5 2 6
C A,B 5 4 7

For the same project, if we work with the pessimistic worst case estimate and use critical path method, what is the project completion time calculated by CPM?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!