Question: Activity Depends on Duration Estimate(most likely Duration Estimate(best case) Duration Estimate( worst case) A - 4 2 8 B - 5 2 6 C A,B
| Activity | Depends on | Duration Estimate(most likely | Duration Estimate(best case) | Duration Estimate( worst case) |
| A | - | 4 | 2 | 8 |
| B | - | 5 | 2 | 6 |
| C | A,B | 5 | 4 | 7 |
For the same project, if we work with the pessimistic worst case estimate and use critical path method, what is the project completion time calculated by CPM?